Raiwasa and Cakobau road works completed

The Raiwasa road in the central division has be re-opened to traffic after repairs to the collapsed retaining wall were completed last month. In a statement, Fiji Roads Authority’s (FRA) Maintenance Works Manager Mr Aram Goes said quality structural repairs in urban areas is important to improve and maintain the condition of the existing road […]

Nacanieli Tuilevuka

July 5, 2016 9:12 am

The Raiwasa road in the central division has be re-opened to traffic after repairs to the collapsed retaining wall were completed last month.

Fiji Roads Authority Representative Jaashinta Ben at Raiwasa Road, Suva. (FRA)
Fiji Roads Authority Representative Jaashinta Ben at Raiwasa Road, Suva. (FRA)

In a statement, Fiji Roads Authority’s (FRA) Maintenance Works Manager Mr Aram Goes said quality structural repairs in urban areas is important to improve and maintain the condition of the existing road assets.

GOES: “Now both the road and the park below, can be used safely for many more years to come.”

Meanwhile, rehabilitation work on Cakobau Road in Suva is also complete and open to traffic.

Fiji Roads Authority Representative Jaashinta Ben at Cakobau Road, Suva. (FRA)
Fiji Roads Authority Representative Jaashinta Ben at Cakobau Road, Suva. (FRA)

Mr Goes said these planned works have upgraded the existing road surface, creating a smoother and safer journey for motorists, including increased roadside parking space for the public.

Maintenance work on the Raiwasa Road is expected to be completed by Wednesday the 8th of June 2016.

FRA’s contractors Fulton Hogan Hiways carrying out maintenance work at Raiwasa Road. (FRA)
FRA’s contractors Fulton Hogan Hiways carrying out maintenance work at Raiwasa Road. (FRA)

In a statement Fiji Roads Authority’s Maintenance Works Manager Mr Aram Goes said the Road is closed and only a pedestrian path is open.

GOES: “This is an important maintenance work that will ensure that the road, and the park below, can be used safely for many more years to come.”

He said the work has been met with very positive feedback from local businesses and residents.

GOES: “We have had a slight delay in completing the road works due to the adverse weather conditions earlier last month however we are now on schedule, following the recent steady period of good weather.”

Mr Goes said the detour road is through the Park Road and they are advising the road users to proceed with caution whilst the work is in progress.

GOES: “The Raiwasa Road is in the final stages of completion, it’s looking good and we wish to thank the public for their patience.”